(i) You are the cost Engineer for a construction company in charge of building a new bridge. The construction company will be penalized each day of delay in
construction for bridge. The penalty will be $4500 for the first day and will increase
by $12000 for each following day. Based on its budget, the company can afford to
pay a maximum of $ 155000 toward penalty. By modelling this as an arithmetic
progression, find the maximum number of days by which the completion of work can
be delayed.

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 22.06.2019 00:50, meganwintergirl
4. a single woman uses an online cash flow calculator which reveals a cash flow of 203. what does this mean?
Answers: 3
image
Mathematics, 22.06.2019 02:30, kam110800
Jennifer is 20 miles north of her house, and she is driving north on the highway at a rate of 55 miles per hour whats the slpoe
Answers: 2
image
Mathematics, 22.06.2019 03:10, bree249
Write the point slope form of the equation of the line passing through the points (-5, 6) and (0.1).
Answers: 2
image
Mathematics, 22.06.2019 04:00, rebeccamckellpidge
Its due 1. what is the product of 1/2-1/4? write your answer in standard form. a) show your work. b) is the product of 1/2x-1/4 and 5x^2-2x+6 equal to product of 1/4x-1/2 and 5x^2-2x+6? explain your answer.
Answers: 1
You know the right answer?
(i) You are the cost Engineer for a construction company in charge of building a new bridge. The co...

Questions in other subjects:

Konu
Mathematics, 13.10.2020 14:01