Hayden is a manager at a landscaping company. he has 3 workers to
landscape an entire park, cody, kaitlyn, and joseph. cody can complete
the project in 8 hours. kaitlyn can complete the project in 6 hours.
joseph is new, so no one knows how long it will take him.
hayden
assigns all of them to complete the park together. explain to hayden
how this project can tell him how long it would take joseph to complete
the project if he worked by himself. use complete sentences.

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, ajl05
Christine went shopping and bought each of her six six nephews a? gift, either a video costing? $14.95 or a cd costing? $16.88. she spent ? $ 97.42 97.42 on the gifts. how many videos and how many cds did she? buy?
Answers: 1
image
Mathematics, 21.06.2019 15:30, edgarnino13
Maria donates a fixed amount, a, to a charity each month. if she donates $300 in 12 months, what is the equation for a? a. a + 300 = 12 b. a × 300 = 12 c. a × 12 = 300 d. a + 12 = 300 e. a + 32 = 100
Answers: 3
image
Mathematics, 21.06.2019 16:30, khush77
Problem melissa is her dad build a walkway in their backyard. the walkway will be 54 feet long and 1.5 feet wide. the local hardware store sells tiles which are 1.5 by 1.5 feet and come in boxes of 12. how many boxes of tiles do they need?
Answers: 1
image
Mathematics, 21.06.2019 17:00, danjan9084
Aplane flies around trip to philadelphia it flies to philadelphia at 220 miles per hour and back home with a tailwind at 280 miles per hour if the total trip takes 6.5 hours how many miles does the plane fly round trip
Answers: 1
You know the right answer?
Hayden is a manager at a landscaping company. he has 3 workers to
landscape an entire park, c...

Questions in other subjects: