The amount of time needed to complete a job, t, varies inversely with the number of workers, w. If 11 workers can complete a job in 39 minutes. How many minutes would it take 13 workers?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:00, clarkster112679
1- identificar select the category that corresponds to each term. january 23 11: 59 pm unlimited attempts remaining grade settings 276-279 vocabulary list modelo fiesta quinceañera casada adolescencia viudo juventud navidad niñez vejez aniversario de bodas divorciado madurez cumpleaños soltera
Answers: 2
image
Mathematics, 21.06.2019 18:00, ReeseMoffitt8032
In a graph with several intervals o data how does a constant interval appear? what type of scenario produces a constant interval?
Answers: 1
image
Mathematics, 21.06.2019 21:10, mauricio18s
Determine the solution for mc001-1.jpeg
Answers: 1
image
Mathematics, 21.06.2019 21:30, unknowntay04
Which equation shows the variable terms isolated on one side and the constant terms isolated on the other side for the equation -1/2x+3=4-1/4x? a. -1/4x=1 b. -3/4x=1 c. 7=1/4x d. 7=3/4x
Answers: 1
You know the right answer?
The amount of time needed to complete a job, t, varies inversely with the number of workers, w. If 1...

Questions in other subjects:

Konu
Spanish, 18.03.2021 01:30