Mathematics, 20.06.2020 22:57 bneilesauger

Consider the following work breakdown structure: Time Estimates (days) LikelyPessimisticStartA, B - - - AC, D 44 50 56 BD 45 60 75 CE 42 45 48 DF 31 40 49 EF 27 36 39 FEnd 58 70 82 What is the probability that the critical path for this project will be completed within 210 days

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, ddoherty88
How much dextrose 70% must be mixed with dextrose 5% to prepare 1,000 ml of dextrose 20%?
Answers: 1
image
Mathematics, 21.06.2019 20:00, quarrella
Adam used 1072.4 gallons of water over the course of 7 days. how much water did adam use, on average, each day?
Answers: 1
image
Mathematics, 21.06.2019 20:30, thefish81
Interest begins accruing the date of the transaction except for auto loans mortgages credit card cash advances credit card purchases
Answers: 1
image
Mathematics, 21.06.2019 23:10, jaylenmiller437
Astudent draws two parabolas on graph paper. both parabolas cross the x-axis at (–4, 0) and (6, 0). the y-intercept of the first parabola is (0, –12). the y-intercept of the second parabola is (0, –24). what is the positive difference between the a values for the two functions that describe the parabolas? write your answer as a decimal rounded to the nearest tenth
Answers: 2
You know the right answer?
Consider the following work breakdown structure: Time Estimates (days) LikelyPessimisticStartA, B -...