A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. 1) Draw the project network. Complete the project schedule
2) can they complete the project in 30 days?
3) Critical path is?
4) Which activity has the most slack?
Solve without using computer
Activity Time Immediate Predecessor
A. Find client 4
B. Write prospectus 2 A
C. Obtain approval from client and professor 3 B
D. Complete programming 12 C
E. Do industry background research 10
F. Write final paper 6 D, E
G. Write oral report 5 D, E

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 20.06.2019 18:02, hlc614
Find the domain of the function  [tex]f(x) = \sqrt{3x - 7} [/tex]in interval form, the domain of f is what? in advance.
Answers: 1
image
Mathematics, 21.06.2019 13:30, TheOneandOnly003
Which statement is not always true for a parallelogram? (a) opposite sides are congruent. (b) diagonals bisect each other. (c) it has 4 congruent angles. (d) consecutive angles are supplementary.
Answers: 1
image
Mathematics, 21.06.2019 18:00, evanwall91
Need on this geometry question. explain how you did it.
Answers: 2
image
Mathematics, 21.06.2019 21:30, iamhayls
Mama mia restaurant used 1 2 2 1 ? of their mozzarella cheese making pizza and the remaining 6 4 64 ounces making pasta. how many pounds of mozzarella cheese did mama mia start with?
Answers: 1
You know the right answer?
A senior MIS design class project team has developed the following schedule of activities for their...

Questions in other subjects:

Konu
Biology, 22.09.2019 08:10