A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required.
1) Draw the project network. Complete the project schedule
2) can they complete the project in 30 days?
3) Critical path is?
4) Which activity has the most slack?
Solve without using computer
Activity Time Immediate Predecessor
A. Find client 4
B. Write prospectus 2 A
C. Obtain approval from client and professor 3 B
D. Complete programming 12 C
E. Do industry background research 10
F. Write final paper 6 D, E
G. Write oral report 5 D, E
Answers: 2
Mathematics, 21.06.2019 13:30, TheOneandOnly003
Which statement is not always true for a parallelogram? (a) opposite sides are congruent. (b) diagonals bisect each other. (c) it has 4 congruent angles. (d) consecutive angles are supplementary.
Answers: 1
Mathematics, 21.06.2019 18:00, evanwall91
Need on this geometry question. explain how you did it.
Answers: 2
A senior MIS design class project team has developed the following schedule of activities for their...
Mathematics, 22.09.2019 08:10
World Languages, 22.09.2019 08:10
Biology, 22.09.2019 08:10
History, 22.09.2019 08:10
History, 22.09.2019 08:10