The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash Max Days
by 1 day to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
A. What is the critical path of this project?
The following table provides a description for the project Z.
Activity/ Duration/ Predecessor/ Cost to crash Max Days
by 1 day/ to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
B. What is the duration of this project?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, vnzgirl
1. there are 25 students who started computer programming in elementary school and 25 students who started computer programming in middle school. the first group had a mean final project grade of 95% and the second group had a mean final project grade of 92%. the line plot shows the differences after 10 rerandomizations. determine whether the difference in the means of the two groups is significant based on the line plot. explain your answer.
Answers: 1
image
Mathematics, 21.06.2019 16:00, soso585oo
The graph shows the function f(x) = (2.5)x was horizontally translated left by a value of h to get the function g(x) = (2.5)x–h.
Answers: 1
image
Mathematics, 21.06.2019 17:00, hsernaykaw42
Use the frequency distribution, which shows the number of american voters (in millions) according to age, to find the probability that a voter chosen at random is in the 18 to 20 years old age range. ages frequency 18 to 20 5.9 21 to 24 7.7 25 to 34 20.4 35 to 44 25.1 45 to 64 54.4 65 and over 27.7 the probability that a voter chosen at random is in the 18 to 20 years old age range is nothing. (round to three decimal places as needed.)
Answers: 1
image
Mathematics, 21.06.2019 21:40, melinalange48
What is the value of x in the equation 1.5x+4-3=4.5(x-2)?
Answers: 2
You know the right answer?
The following table provides a description for the project Z. Activity Duration Predecessor Cost to...

Questions in other subjects:

Konu
Mathematics, 29.08.2020 20:01