Mathematics, 10.06.2020 04:57 BrianKeokot4534
When the two crews start working together, what part of all
the garbage bins will the first garbage truck empty?
The crew of a garbage truck takes 5 hours to empty all the
bins in one neighborhood on pickup day. The city assigned
a second garbage truck to this neighborhood. During their
training, it took the crew from the second truck 8 hours to
empty all the bins.
0.6
0.5
0.7
Time
(hours)
t
Part of Bins
Emptied
Rate
(part/hour)
1
5
0.4
First Truck
500
(9
1
t
Second
Truck
1
8
8
Answers: 1
Mathematics, 21.06.2019 22:30, lilmaddy8856
Which expressions equal 9 when x=4 and y=1/3 a. x2+6y b. 2x + 3y c. y2-21x d. 5 (x/2) -3y e. 3x-9y
Answers: 2
Mathematics, 22.06.2019 03:00, mmcdaniels46867
Aquality characteristic of new iphone x made at the amsterdam plant at apple computers has a manufacturing specification (in mm) of 0.200 +/- .07. historical data indicates that if the quality characteristic takes on values greater than 0.27 or smaller than 0.13 the component fails at a cost of20.19. based on these data: determine the taguchi loss function (must show work) calculate an estimated loss for a quality characteristic of .30 calculate an estimated loss for quality characteristic of .40.
Answers: 2
When the two crews start working together, what part of all
the garbage bins will the first garbage...
Mathematics, 20.09.2020 14:01
Mathematics, 20.09.2020 14:01
Mathematics, 20.09.2020 14:01
Mathematics, 20.09.2020 14:01