A welder produces 7 welded assemblies during the first day on a new job, and the seventh assembly takes 45 minutes (unit time). The worker produces 10 welded assemblies on the second day, and the 10th assembly on the second day takes 30 minutes. Given this information, (a) what is the percent learning rate and (b) what is the total cumulative time to produce all 17 welded assemblies

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, jennsou
The system of equations graphed below has how many solutions?
Answers: 1
image
Mathematics, 21.06.2019 15:30, nisha87
Which of the following statements is not true? a. parallel lines are lines in the same plane that never intersect. b. congruent figures have the same shape and same size angles and sides. c. similar figures must have the same shape and the same size. d. a rotation is when you turn a figure around a certain point.
Answers: 1
image
Mathematics, 21.06.2019 19:00, Keekee9847
What is the equation of the line in point-slope form? y+ 4 = 1/2(x+4) y-4 = 1/2(x + 4) y-0 = 2(x - 4) y-4 = 2(8-0)
Answers: 2
image
Mathematics, 21.06.2019 20:40, leo4687
The acceleration of an object due to gravity is 32 feet per second squared. what is acceleration due to gravity in inches per second squared?
Answers: 2
You know the right answer?
A welder produces 7 welded assemblies during the first day on a new job, and the seventh assembly ta...

Questions in other subjects: