In a certain manual operation, the first work unit required 7.83 min to complete and the learning rate is known to be 84% in the Wright model. Using this learning curve model, determine the average cumulative times to produce (a) the second unit, (b) the 10th unit, and (c) the 100th unit. (d) Find the total cumulative time for the 100 units and the unit time for the 100th unit.

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, lm18618
Jeffery conducted a survey in his school and found that 30 of the 50 eighth grade students' favorite subject is mathematics. based on the results, jeffery concluded that out of the 200 students in his school, 120 students' favorite subject is mathematics. select the statement that is true about jeffery's conclusion. a. jeffery's conclusion is not valid because the sample was biased since only 200 students were surveyed. b. jeffery's conclusion is valid because the sample was random since all of the students were eighth grade students. c. jeffery's conclusion is valid because the sample was random. d. jeffery's conclusion is not valid because the sample was biased since all of the students were eighth grade students.
Answers: 2
image
Mathematics, 21.06.2019 19:30, sweetbri7p5v6tn
Aline passes through 3,7 and 6,9 what equation represents the line
Answers: 2
image
Mathematics, 21.06.2019 23:50, zariyastanfield4452
The graph of a curve that passes the vertical line test is a:
Answers: 3
image
Mathematics, 22.06.2019 00:00, yaz1206
Stefanie is painting her bedroom. she can paint 2 1/3 square feet in 4/5 of an hour. how many square feet can she paint in one hour?
Answers: 2
You know the right answer?
In a certain manual operation, the first work unit required 7.83 min to complete and the learning ra...

Questions in other subjects:

Konu
Social Studies, 13.10.2020 06:01