Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:30, Greekfreak
To determine the number of deer in a forest a forest ranger tags 280 and releases them back
Answers: 3
image
Mathematics, 21.06.2019 21:30, mrlepreqon8897
Apool measures 100 meters by 100 meters a toddler inside the pool and trows a ball 60 centimeters from one edge of the pool. how far is the ball from the opposite edge of the pool
Answers: 1
image
Mathematics, 21.06.2019 21:30, GreenHerbz206
Find the unit rate for: 75% high-fiber chimp food to 25% high -protein chimp food.
Answers: 2
image
Mathematics, 21.06.2019 21:40, lineaeriksen
Ineed your ! i was to turn this into pond first thing i gotta do is outline the inside with this plastic how big should i cut the plastic the height: 10 1/2” the length: 40” the width: 12” me !
Answers: 1
You know the right answer?
Suppose it is now the end of the seventh day and that activities A and B have been completed while a...

Questions in other subjects:

Konu
Mathematics, 27.01.2020 21:31