The time t (in weeks) it takes workers to complete a project varies inversely with the number n of workers. It takes 6 workers 6 weeks to complete the project. Write an inverse variation equation that relates t and n.
Answers: 2
Mathematics, 22.06.2019 00:30, bobby237065
Three friends are comparing the prices of various packages of golf balls at a sporting goods store. hector finds a package of 6 golf balls that costs $4.50.
Answers: 3
Mathematics, 22.06.2019 02:00, AnastasiaJauregui
If p(x) is the total value of the production when there are x workers in a plant, then the average productivity of the workforce at the plant is a(x) = p(x) x . (a) find a'(x). a'(x) = xp'(x) − p(x) x a'(x) = xp'(x) − p(x) x2 a'(x) = p'(x) − p(x) x a'(x) = xp'(x) − p'(x) x2 a'(x) = p'(x) − xp(x) x2 why does the company want to hire more workers if a'(x) > 0? a'(x) > 0 ⇒ a(x) is ; that is, the average productivity as the size of the workforce increases. (b) if p'(x) is greater than the average productivity, which of the following must be true? p'(x) − xp(x) > 0 p'(x) − xp(x) < 0 xp'(x) − p'(x) > 0 xp'(x) − p(x) < 0 xp'(x) − p(x) > 0
Answers: 2
The time t (in weeks) it takes workers to complete a project varies inversely with the number n of w...
Mathematics, 10.02.2021 18:40
Physics, 10.02.2021 18:40
History, 10.02.2021 18:40
History, 10.02.2021 18:40
Mathematics, 10.02.2021 18:40
Mathematics, 10.02.2021 18:40
Biology, 10.02.2021 18:40
Mathematics, 10.02.2021 18:40