A project has three paths and a desired completion time of 43 days. The first path has a 70 percent probability of being completed in 43 days. The second has an 85 percent probability and the third haws a 90 percent probability. What is the probability that the project will be completed on time

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 12:30, trapqueenriz12
Arunning track in the shape of an oval is shown. the ends of the track form semicircles. a running track is shown. the left and right edges of the track are identical curves. the top and bottom edges of the track are straight lines. the track has width 56 m and length of one straight edge 130 m. what is the perimeter of the inside of the track? (π = 3.14) 260.00 m 347.92 m 372.00 m 435.84 m
Answers: 1
image
Mathematics, 21.06.2019 22:30, Edwardwall
What three-dimensional solid have 6 rectangular faces, 2 equal bases that are not rectangles and 18 edges
Answers: 3
image
Mathematics, 21.06.2019 23:00, aisha82
Square a has a side length of (2x-7) and square b has a side length of (-4x+18). how much bigger is the perimeter of square b than square a?and show all work! you so
Answers: 2
image
Mathematics, 22.06.2019 00:50, 20alyssityh224
Arectangle has a perimeter of 24 inches. if the width is 5 more than twice the length, what are the dimensions of the rectangle?
Answers: 3
You know the right answer?
A project has three paths and a desired completion time of 43 days. The first path has a 70 percent...

Questions in other subjects:

Konu
Mathematics, 10.02.2021 19:20