When building a house, the number of days required to build varies inversely with
with the number of workers. One house was built in 20 days by 19 workers. How
many days would it take to build a similar house with 38 workers?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 20.06.2019 18:04, giulissaf
What is the value of 1/3× + 7x, when x =5
Answers: 1
image
Mathematics, 21.06.2019 14:30, smolemily
Find the value of tan theta if sin theta = 12/13 and theta is in quadrant 2
Answers: 3
image
Mathematics, 21.06.2019 17:00, marleas
Bugs bunny was 33 meters below ground, digging his way toward pismo beach, when he realized he wanted to be above ground. he turned and dug through the dirt diagonally for 80 meters until he was above ground
Answers: 3
image
Mathematics, 21.06.2019 23:00, Lizethh1
Acaterer knows he will need 60, 50, 80, 40 and 50 dinner napkins on five successive evenings. he can purchase new napkins initially at 25 cents each, after which he can have dirty napkins laundered by a fast one-day laundry service (i. e., dirty napkins given at the end of the day will be ready for use the following day) at 15 cents each, or by a slow two-day service at 8 cents each or both. the caterer wants to know how many napkins he should purchase initially and how many dirty napkins should be laundered by fast and slow service on each of the days in order to minimize his total costs. formulate the caterer’s problem as a linear program as follows (you must state any assumptions you make): a. define all variables clearly. how many are there? b. write out the constraints that must be satisfied, briefly explaining each. (do not simplify.) write out the objective function to be minimized. (do not simplify.)
Answers: 1
You know the right answer?
When building a house, the number of days required to build varies inversely with
with the num...

Questions in other subjects: