An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pessimistic estimate of 34 days. What is the expected duration of the activity

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, mustafajibawi1
A(t)=728(1+0.04)^t how much money did aditya originally invest
Answers: 1
image
Mathematics, 21.06.2019 17:00, val186
Marlow is comparing the prices of two trucks rental compaines company a charges $3 per hour and an addtional $75 as serivce charges company b charges $2 per hour and an additional $85 as serivce charges
Answers: 1
image
Mathematics, 21.06.2019 19:00, alyea231
What are the first 4 terms in the multiplication pattern given by the formula 2×4n
Answers: 1
image
Mathematics, 22.06.2019 02:00, sarbjit879
Hurry can a triangle can be constructed with angles measuring 115°,55°, and 20°? yes or no
Answers: 2
You know the right answer?
An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pes...

Questions in other subjects:

Konu
Mathematics, 29.04.2021 01:00
Konu
Mathematics, 29.04.2021 01:00