Mathematics, 12.03.2020 06:40 ingridx0

16.4 A 12-station automated production line has an ideal cycle time of 24 sec. Line stops occur on average once every 20 cycles. When a line stop occurs, average downtime is 3.0 min. Cost of each starting work part is $1.55, and the cost to operate the line is $66/hr. Tooling cost is $0.13 per work part. Determine (a) average hourly production rate, (b) line efficiency, and (c) cost of a workpiece produced.

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:50, hernsl0263
Which three lengths could be the lengths of the sides of a triangle? 21 cm, 7 cm, 7 cm 9 cm, 15 cm, 22 cm 13 cm, 5 cm, 18 cm 8 cm, 23 cm, 11 cm
Answers: 2
image
Mathematics, 21.06.2019 21:30, achsahjosey
Acyclist bike x distance at 10 miles per hour .and returns over the same path at 8 miles per hour. what is the cyclist average rate for the round trip in miles per hour ?
Answers: 1
image
Mathematics, 21.06.2019 23:00, kaleahlove13
Delbert keeps track of total of the total number of points he earns on homework assignments, each of which is worth 60 points. at the end of the semester he has 810 points. write an equation for delbert’s average homework score a in terms of the number of assignments n.
Answers: 3
image
Mathematics, 21.06.2019 23:30, ramandeep
Write a similarity statement for the similar triangles. afgh ~ a
Answers: 1
You know the right answer?
16.4 A 12-station automated production line has an ideal cycle time of 24 sec. Line stops occur on a...

Questions in other subjects: