The navy contract was for 2,314 devices and took 23 workers two weeks (40 hours per week) to complete. The army contract was for 4,707 devices that were produced by 16 workers in three weeks. What's the productivity of the army contract for the input of labor hours

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:00, cookies1164
What is the maximum total area that 450cm of string can enclose if it is used to form perimeters of two adjoining rectangles as shown?
Answers: 1
image
Mathematics, 21.06.2019 19:00, nateqqj
Prove that quadrilateral is a rhombus.
Answers: 1
image
Mathematics, 21.06.2019 21:10, verdolaga2017me
What is the domain of the given function? {(3,-2), (6, 1), (-1, 4), (5,9), (-4, 0); o {x | x= -4,-1, 3, 5, 6} o {yl y = -2,0, 1,4,9} o {x|x = -4,-2, -1,0, 1, 3, 4, 5, 6, 9} o y y = 4,-2, -1, 0, 1, 3, 4, 5, 6, 9}
Answers: 1
image
Mathematics, 22.06.2019 01:00, powella033
Azul has 4 green picks and no orange picks. you add orange picks so that there are 2 orange picks for every 1 green pick. how many picks are there now.
Answers: 2
You know the right answer?
The navy contract was for 2,314 devices and took 23 workers two weeks (40 hours per week) to complet...

Questions in other subjects:

Konu
Mathematics, 31.03.2021 14:00