A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, faithrawlins14
I’m which figure is point g an orthocenter
Answers: 1
image
Mathematics, 21.06.2019 18:30, alizeleach0123
Which representation has a constant of variation of -2.5
Answers: 1
image
Mathematics, 21.06.2019 19:50, jaquonb23
Which inequality is equivalent to -3x < -12? x < 4 , x < -4 , x > 4, x > -4
Answers: 1
image
Mathematics, 21.06.2019 21:50, edjiejwi
Aline passes through the point (–7, 5) and has a slope of 1/2 which is another point that the line passes through?
Answers: 3
You know the right answer?
A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance...

Questions in other subjects:

Konu
English, 20.09.2020 07:01
Konu
Mathematics, 20.09.2020 07:01