A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?
Answers: 2
Mathematics, 21.06.2019 18:30, alizeleach0123
Which representation has a constant of variation of -2.5
Answers: 1
A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance...