The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:30, amylumey2005
What can each term of the equation be multiplied by to eliminate the fractions before solving? x – + 2x = + x 2 6 10 12
Answers: 2
image
Mathematics, 21.06.2019 19:00, morgeron6071
Which statement best explains why ben uses the width hi to create the arc at j from point k
Answers: 2
image
Mathematics, 21.06.2019 23:30, shady1095
Asap (i need to finish this quick) graph complete the sequence of transformations that produces △x'y'z' from △xyz. a clockwise rotation ° about the origin followed by a translation units to the right and 6 units down produces δx'y'z' from δxyz.
Answers: 1
image
Mathematics, 22.06.2019 00:00, staz13wiggins
Why is x= 4 a solution to the proportion 14/x 56/1 6
Answers: 1
You know the right answer?
The time required to complete a project is normally distributed with a mean of 80 weeks and a standa...

Questions in other subjects:

Konu
Mathematics, 11.02.2021 17:40
Konu
Mathematics, 11.02.2021 17:40