A PERT analysis of a small project determined that the duration of the critical path is 10 weeks with a variance of 2 weeks. What project duration can be promised that will have only a 5% chance of time overrun?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, avadestinyy
Find the midpoint m of z1=(8+5i) and z2=(12+3i)
Answers: 1
image
Mathematics, 21.06.2019 19:00, vane6176
Which sentence uses an objective tone? we will plant the best garden of any school in the area. the new campus garden will surely be envied by other schools. a garden would provide numerous benefits to the students. you will probably agree that gardens have many benefits.
Answers: 3
image
Mathematics, 21.06.2019 20:00, suselygonza
Compare the following pair of numbers a and b in three ways. a. find the ratio of a to b. b. find the ratio of b to a. c. complete the sentence: a is percent of b. a=120 and b=340 a. the ratio of a to b is . b. the ratio of b to a is . c. a is nothing percent of b.
Answers: 1
image
Mathematics, 22.06.2019 01:30, Mah1937
Find the solution to this system 2,1 1,-2 1,2 -1,2
Answers: 1
You know the right answer?
A PERT analysis of a small project determined that the duration of the critical path is 10 weeks wit...

Questions in other subjects:

Konu
English, 10.11.2021 07:50
Konu
Mathematics, 10.11.2021 07:50
Konu
Mathematics, 10.11.2021 08:00