An auto service center that specializes in oil changes has two service bays that serve, on average, a total of 24 cars per eight-hour business day. On average, each bay can finish one oil change in 30 minutes.

What is the design capacity? 30 min per oil change per bay (8 hr day x 2 (30 min each) =16 x 2 bays =?)

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:20, deb2710
Find the slope of a line given the following two points
Answers: 1
image
Mathematics, 21.06.2019 16:30, erbnichole
Solve by any method (graphing, substitution or linear combination)y = x - 82x + 3y = 1a) (2, -6)b) (5, -3)c) (4, -4)d) (0, -8)i figured it out. the answer is (5, -3)
Answers: 1
image
Mathematics, 21.06.2019 20:00, rosaura15
If the discriminant if a quadratic equation is 4 which statement describes the roots?
Answers: 3
image
Mathematics, 22.06.2019 01:30, bobjill1609
Sara goes on a slingshot ride in an amusement park. she is strapped into a spherical ball that has a radius 3*10^2 of centimeters. what is the volume of air in the spherical ball? use this formula: volume of a sphere=4/3pi, r^3 , where r is the sphere’s radius.
Answers: 1
You know the right answer?
An auto service center that specializes in oil changes has two service bays that serve, on average,...

Questions in other subjects:

Konu
Mathematics, 28.03.2020 00:01