Suppose a particular project has an expected completion time of 30 days; in other words, the critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this information, please answer the following questions:

Find the probability that the project:
(1) Would be completed within 40 days
(2) Would take longer than 40 days to finish
(3) Would be completed within 20 days
(4) Would take longer than 20 days to finish

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:30, DJEMPGYT
Will give are given that xy is parallel to zw. if xz is a transversal that intercepts xy and zw, angle angle alternate interior angles. since xy is parallel to zw, we know that these angles are we also know that angle xvy and angle zvw are , and thus congruent. we can conclude that △xyv ~ △zwv using the similarity theorem.
Answers: 2
image
Mathematics, 21.06.2019 17:00, alexabdercmur
You are a clerk at convenience store. a customer owes 11.69 for a bag of potatoes chips. she gives you a five dollar bill. how much change should the customer receive?
Answers: 2
image
Mathematics, 21.06.2019 18:00, lexis1446
Which represents the solution set of the inequality 5x-9 < 21? a. x < 12/5 b. x > 12/5 c. x > 6 d. x < 6
Answers: 2
image
Mathematics, 21.06.2019 18:30, anishivaturi123
Select the lengths in centimeters that would form a right triangle
Answers: 1
You know the right answer?
Suppose a particular project has an expected completion time of 30 days; in other words, the critica...

Questions in other subjects:

Konu
Mathematics, 02.06.2020 00:58
Konu
Computers and Technology, 02.06.2020 00:58
Konu
Mathematics, 02.06.2020 00:58