Mathematics, 29.10.2019 16:31 babylear
Person 1 can do a certain job in 16 minutes, and person 2 can do the same job in 24 minutes. when completing the job together, which expression would be used to represent the amount of work done by person 1?
a. 16
b. 1/16
c. x/16
d. 16x
Answers: 2
Mathematics, 21.06.2019 20:30, jmcd10
Create a question with this scenario you could ask that could be answered only by graphing or using logarithm. david estimated he had about 20 fish in his pond. a year later, there were about 1.5 times as many fish. the year after that, the number of fish increased by a factor of 1.5 again. the number of fish is modeled by f(x)=20(1.5)^x.
Answers: 1
Mathematics, 21.06.2019 22:10, oijhpl5085
Using graph paper, determine the line described by the given point and slope. click to show the correct graph below.(0, 0) and 2/3
Answers: 2
Person 1 can do a certain job in 16 minutes, and person 2 can do the same job in 24 minutes. when co...
Mathematics, 19.03.2021 21:40
Mathematics, 19.03.2021 21:40
Mathematics, 19.03.2021 21:40
Mathematics, 19.03.2021 21:40
Mathematics, 19.03.2021 21:40
Mathematics, 19.03.2021 21:40
Chemistry, 19.03.2021 21:40