Consider the following work breakdown structure:
duration estimates days
activity precedes optimistic most likely pessimistic
start u, v - - -
u w 35 50 65
v w, x 28 40 52
w z 26 35 44
x y 28 40 52
y z 26 29 38
z end 36 60 84
what is the estimated expected (mean) time for project completion?
a. 135 days
b. 145 days
c. 170 days 1
d. 80 days
e. 255 days

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, rbgrh9465
Which of these is and example of a literal equation? a) 6+30=6^2 b)3x-4y c)12=9+3x d)ax-by=k
Answers: 3
image
Mathematics, 21.06.2019 18:00, kellysmith45
The chs baseball team was on the field and the batter popped the ball up. the equation b(t)=80t-16•16+3.5 represents the height of the ball above the ground in feet as a function of time in seconds. how long will the catcher have to get in position to catch the ball before it hits the ground? round to the nearest second
Answers: 3
image
Mathematics, 21.06.2019 19:10, imran2k13
The linear combination method is applied to a system of equations as shown. 4(.25x + .5y = 3.75) → x + 2y = 15 (4x – 8y = 12) → x – 2y = 3 2x = 18 what is the solution of the system of equations? (1,2) (3,9) (5,5) (9,3)
Answers: 1
image
Mathematics, 21.06.2019 21:00, Neko1kat
Solve this problem! extra ! 3025/5.5 = a/90.75
Answers: 1
You know the right answer?
Consider the following work breakdown structure:
duration estimates days
activity prece...

Questions in other subjects:

Konu
Mathematics, 25.03.2020 20:57