Atotal of 13,000 sheet metal stampings must be produced in the press department during the next three days. manually operated presses (one operator per press) will be used to complete the job and the cycle time is 27 sec. each press must be set up with a punch-and-die set before production starts. setup time is 2.0 hr, and availability is assumed to be 100%. how many presses and operators must be devoted to this production during the three days, if there are 7.5 hr of available time per machine per day?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:30, daquanmcqueen77
Are triangles the congruent? write the congruency statement. what is the congruency that proves they are congruent? what is the perimeter of ∆pqr?
Answers: 1
image
Mathematics, 21.06.2019 22:10, bigboss3026
Which of the following circles have their centers in the third quadrant?
Answers: 2
image
Mathematics, 21.06.2019 23:30, Krazyyykiddd
Xy x xy if a and b are positive integers such that a*b=9 and b*a=72 what is the value of a/b
Answers: 3
image
Mathematics, 22.06.2019 01:30, colebash88
Paco orders an ice cream for $1, but realizes his wallet is at home and he only has 3/20 of $1 with him. if his mom pays the remaining 7/20 of the dollar, how much will she pay? $0.05 $0.15 $0.85 $0.95
Answers: 1
You know the right answer?
Atotal of 13,000 sheet metal stampings must be produced in the press department during the next thre...

Questions in other subjects:

Konu
Mathematics, 28.01.2021 17:30
Konu
Mathematics, 28.01.2021 17:30
Konu
Mathematics, 28.01.2021 17:30
Konu
Mathematics, 28.01.2021 17:30