Mathematics, 27.11.2019 06:31 koolja3

When building a house, the number of days required to build varies inversely with with the number of workers. one house was built in 76 days by 10 workers. how many days would it take to build a similar house with 20 workers?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:30, nvc1127
2. explain in words how you plot the point (4, −2) in a rectangular coordinate system.
Answers: 1
image
Mathematics, 21.06.2019 21:00, mccdp55
Select the correct answer from each drop-down menu. a system of equations and its solution are given below. system a complete the sentences to explain what steps were followed to obtain the system of equations below. system b to get system b, the equation in system a was replaced by the sum of that equation and times the equation. the solution to system b the same as the solution to system a.]
Answers: 1
image
Mathematics, 21.06.2019 22:30, jadeochoa4466
Aflagpole broke in a storm. it was originally 8 1 81 feet tall. 2 8 28 feet are still sticking straight out of the ground, where it snapped, but the remaining piece has hinged over and touches the ground some distance away. how far away is the end of the pole from the base of the pole along the ground?
Answers: 1
image
Mathematics, 21.06.2019 23:30, georgesarkes12
Oliver had $50 on the day before his birthday. after he recived some money for his birthday , he had $75. write and solve eqaution to find how much money oliver received for his birthday. x+50=75
Answers: 1
You know the right answer?
When building a house, the number of days required to build varies inversely with with the number of...