All the members of a construction crew work at the same pace. six of them working together are able to pour foundation in 22 hours. how many hours would this job take if the number of workers decreased by factor of 2, increased by 2, and increased by 4?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, britneyvaughn219
Agraph of a trapezoid can have diagonals with slopes that are negative reciprocals and two pairs of adjacent sides that are congruent, true or false, and why
Answers: 1
image
Mathematics, 21.06.2019 22:40, 721345
What is the the greatest common factor ?
Answers: 2
image
Mathematics, 21.06.2019 23:50, Animallover100
What is the inverse of f(x) = 6x -24
Answers: 1
image
Mathematics, 22.06.2019 02:00, redbenji1687
35 ! insert < , > , or = to make the sentence true. 12 __ 25 > =
Answers: 1
You know the right answer?
All the members of a construction crew work at the same pace. six of them working together are able...

Questions in other subjects: