Mathematics, 25.10.2019 23:43 battlemarshmell

Afilter has been designed to have a run length of 48 hr while operating at a filtration rate of 12 m/h. the design backwash rate is 40 m/h, backwash duration is 15 min, and filter-to-waste duration is 10 min. the plant operators decided to clean the filters more thoroughly and they backwash at a rate of 55 m/h for 25 min. as a result, ripening takes longer and the filter-to-waste duration is 50 min. calculate the ufrv, ubwv, ufwv, and recovery (a) as designed and (b) as operated. what is the percent increase in the volume of treated water lost as waste backwash water and filter-to-waste water?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:30, natebarr17
The interior angles formed by the side of a hexagon have measures of them up to 720° what is the measure of angle a
Answers: 2
image
Mathematics, 21.06.2019 22:00, erinkiing
I’m still confused on how to work the percentages
Answers: 2
image
Mathematics, 21.06.2019 22:30, 19thomasar
Atotal of 766 tickets were sold for the school play. they were either adult tickets or student tickets. there were 66 more student tickets sold than adult tickets. how many adult tickets were sold?
Answers: 1
image
Mathematics, 22.06.2019 02:00, torquishag
Tanyss's house has 25 windows. her brother has washed 22 of the windows. what percent of the windows has her brother washed?
Answers: 1
You know the right answer?
Afilter has been designed to have a run length of 48 hr while operating at a filtration rate of 12 m...