Mathematics, 22.10.2019 19:30 alienxangg91

The formula below used by project managers to compute e, the estimated time to complete a job, where o is the shortest completion time, p is the longest completion time, and m is the most likely completion time. e= o+4m+p 6 what is p in terms of e, o, and m?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:40, marie1211
Polynomial that can be factored as (3x-4)(3x+4)
Answers: 1
image
Mathematics, 21.06.2019 18:50, cmaya
Standard deviation of 19,29,21,22,23
Answers: 1
image
Mathematics, 21.06.2019 19:30, nyceastcoast
Explain how you can find the missing fraction in 3 4/5 / (blank) 2 5/7. then find the missing fraction.
Answers: 2
image
Mathematics, 22.06.2019 03:00, webbhlharryteach
Out of five men and five women, we form a committee consisting of four different people. assuming that each committee of size four is equally likely, find the probabilities of the following events: 1. the committee consists of two men and two women 2. the committee has more women than men. 3. the committee has at least one man. for the remainder of the problem assume that alice and bob are among the ten people being considered. 4. both alice and bob are members of the committee.
Answers: 2
You know the right answer?
The formula below used by project managers to compute e, the estimated time to complete a job, where...