You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. the probability that the project will be completed in 33 days or less is equal
(2 decimal accuracy)

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:40, klrm9792
Use the normal approximation to the binomial distribution to answer this question. fifteen percent of all students at a large university are absent on mondays. if a random sample of 12 names is called on a monday, what is the probability that four students are absent?
Answers: 2
image
Mathematics, 21.06.2019 14:40, alexnunez07
Multiplying an even number of negative numbers gives an answer that is choose from:
Answers: 3
image
Mathematics, 21.06.2019 16:30, kittylover613
Ivan and jeff buy a package of 8 pens for $4.00. ivan wants 5 of the pens, and jeff wants 3.how much should each student pay?
Answers: 1
image
Mathematics, 21.06.2019 21:00, blaqsafire404
Timmy uses 1 1 2 cups of sugar for every 2 gallons of lemonade he makes. how many cups of sugar would timmy use if he makes 13 gallons of lemonade?
Answers: 1
You know the right answer?
You have just used the network planning model and found the critical path length is 30 days and the...

Questions in other subjects:

Konu
Mathematics, 12.04.2021 18:00
Konu
English, 12.04.2021 18:00