The project start on 22/9/2019, we have 221 months to finish the project, knowing that workers work only 6 days a week, when is the due date?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 20.06.2019 18:02, channarlawassociate
Irene bought 3 yards of fabric and a spool of thread for $28.10. if the spool of thread cost $1.25, how much did the fabric cost per yard?
Answers: 2
image
Mathematics, 21.06.2019 14:00, kyusra2008
The graph of a line gets what as the value of the slope gets bigger
Answers: 2
image
Mathematics, 21.06.2019 17:30, Vampfox
Monthly water bills for a city have a mean of $108.43 and a standard deviation of $32.09. find the probability that a randomly selected bill will have an amount greater than $155, which the city believes might indicate that someone is wasting water. would a bill that size be considered unusual?
Answers: 1
image
Mathematics, 21.06.2019 21:40, jacobasencio23
Use sigma notation to represent the following series for 9 terms.
Answers: 2
You know the right answer?
The project start on 22/9/2019, we have 221 months to finish the project, knowing that workers work...

Questions in other subjects:

Konu
Mathematics, 04.10.2020 14:01
Konu
Mathematics, 04.10.2020 14:01