You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. the probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy)
a. 0.73 b. 0.55.c. 0.12 d. 0.27 e. 0.60.
Answers: 2
Mathematics, 21.06.2019 23:00, gisellekatherine1
The equation represents the function f, and the graph represents the function g. f(x)=3(5/2)^x determine the relationship between the growth factors of f and g. a. the growth factor of g is twice the growth factor of f. b. the growth factor of f is twice the growth factor of g. c. the growth factor of f is 2.5 times the growth factor of g. d. the growth factor of f is the same as the growth factor of g.