When building a house, the number of days required to build is inversely proportional to with the number of workers. one house was built in 11 days by 27 workers. how many days would it take to build a similar house with 3 workers?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:20, maisieisdabomb23
What is the measure of ac? 5 units 13 units 26 units 39 units 3x- 2b 6x + 9
Answers: 2
image
Mathematics, 21.06.2019 19:30, LordYoshee8676
Julian wrote the following numeric pattern on the board3,10,17,24,31,38.what numbers of julian's pattern are compound numbers.
Answers: 2
image
Mathematics, 21.06.2019 21:50, amakayla57
What is the next step in the given proof? choose the most logical approach. a. statement: m 1 + m 2 + 2(m 3) = 180° reason: angle addition b. statement: m 1 + m 3 = m 2 + m 3 reason: transitive property of equality c. statement: m 1 = m 2 reason: subtraction property of equality d. statement: m 1 + m 2 = m 2 + m 3 reason: substitution property of equality e. statement: 2(m 1) = m 2 + m 3 reason: substitution property of equality
Answers: 3
image
Mathematics, 21.06.2019 22:30, kdtd3163
In a certain city, the hourly wage of workers on temporary employment contracts is normally distributed. the mean is $15 and the standard deviation is $3. what percentage of temporary workers earn less than $12 per hour? a. 6% b. 16% c. 26% d. 36%
Answers: 1
You know the right answer?
When building a house, the number of days required to build is inversely proportional to with the nu...

Questions in other subjects:

Konu
Geography, 06.05.2020 03:28
Konu
Mathematics, 06.05.2020 03:28
Konu
Mathematics, 06.05.2020 03:28