To fulfill an assignment by a given deadline, a team of workers had to produce 54 parts daily. exceeding the schedule by 6 parts per day, the team not only finished the assignment 1 day earlier, but also produced 18 extra parts. how many days did the team work?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:10, nikolevargas89
How do you answer this question? (step by step)
Answers: 3
image
Mathematics, 21.06.2019 16:00, tdun7003
Find the area and perimeter of each composite figure. use 3.14 for π. round your answer to the nearest tenth. a square and a right triangle share a common side. image long description a 3-meter by 0.5-meter rectangle has triangles attached like wings to the 3-meter sides. the other two sides of both triangles measure 2.5 meters. the height of each triangle is 2 meters. a 6-inch by 4-inch rectangle has 2 half-circles attached like wings to the 6-inch sides. the radius of each half-circle is 3 inches. find the surface area and volume of each figure. use 3.14 for π. round your answer to the nearest tenth. a right circular cylinder has a base radius of 6 yards and a height of 20 yards. a rectangular prism has a base that is 9 centimeters long and 7 centimeters wide. the height is 2 centimeters. a rectangular prism has a base that measures 11 millimeters by 11 millimeters. the height is 11 millimeters.
Answers: 1
image
Mathematics, 22.06.2019 04:00, Annamea
What integer is equivalent to 9 3/2
Answers: 1
image
Mathematics, 22.06.2019 05:00, NathanFrase6770
There are 2 ones, 1 five,3tens, and 1 twenty. if there are 28 bills in her wallet, what would you predict is the approximate value of all the bills
Answers: 1
You know the right answer?
To fulfill an assignment by a given deadline, a team of workers had to produce 54 parts daily. excee...

Questions in other subjects:

Konu
History, 14.04.2020 20:41