A271⁄2-mile stretch of road needs repaving. a company bid on the repaving project, saying they could repave 21⁄4 miles of road per week. how many weeks will the company take to completely repave the stretch of road? a. 151⁄2 b. 121⁄3 c. 131⁄2 d. 122⁄9

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:30, leannhb3162
The bake stars picked 907 apples last weekend at a local orchard they made caramel apples and sold them in the bakery in trays of 6
Answers: 1
image
Mathematics, 21.06.2019 19:00, jackieanguiano3700
Solve the problem. a student earned grades of c, a, b, and a in four different courses. those courses had these corresponding numbers of credit hours: 4, 5, 1, and 5. the grading system assigns quality points to letter grades as follows: a = 4, b = 3, c = 2, d = 1, and f = 0. compute the grade point average (gpa) and round the result to two decimal places. 3.40 3.50 8.75 2.18
Answers: 1
image
Mathematics, 21.06.2019 20:00, lily24113
Put the equation in slope intercept form by solving for y
Answers: 2
image
Mathematics, 21.06.2019 21:10, Anisanene
What is the measure of one interior angle of a pentagon
Answers: 2
You know the right answer?
A271⁄2-mile stretch of road needs repaving. a company bid on the repaving project, saying they could...