Awork cell is scheduled to build 120 digital light processor (dlp) assemblies each week. these assemblies are later installed into home theater projection systems. the work cell has 7.5 hours of productive work each day, six days per week. what is takt time for this cell? express your answer in minutes rounded to one decimal place.