Develop a preliminary WBS for a small one-story commercial building to be constructed on the site of an existing small- frame structure. It is 30 by 60 feet in plan. The 110 Project Planning exterior and interior walls are of concrete block. The roof is constructed of bar joists covered with a steel roof deck, rigid insulation, and built-up roofing. The ceiling is suspended acoustical tile. The floor is a concrete slab on grade with an asphalt tile finish. Interior finish on all walls is paint. Required:
a. Show the first level of this structure for the total project (WBS is developed from top to the bottom).
b. Draw one work package (or building system) of the first level and develop the second-level structure for this work package.

ansver
Answers: 1

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 16:10, TheOriginalMeyah
An electrical motor raises a 50kg load at a construct velencity .calculate the power of the motor, if it takes 40sec to raise the load through a height of 24m(take g =9.8n/g)
Answers: 2
image
Engineering, 04.07.2019 18:20, jessie8022
Apiston-cylinder device contains 0.1 m3 of liquid water and 0.9 m3 of water vapor in equilibrium at 800 kpa. heat is transferred at constant pressure until the temperature of water reaches 350 °c. determine (a) the quality of water at the initial state (b) the work associated with this process, (c) the heat associated with this process.
Answers: 2
image
Engineering, 04.07.2019 19:20, GusGus11
The power source in a certain welding setup generates 3500w that is transferred to the low carbon steel work with a heat transfer factor of 0.85. the melting factor in the operation is 0.45. a continuous fillet weld is to be made with a cross-sectional area of 23 mm2 determine the travel speed at which the welding can be accomplished.
Answers: 3
image
Engineering, 04.07.2019 19:20, carterdaw
Aseries piping system conveys methyl alcohol. the system consists of 70 m of 1- nominal pipe follow by 50 m of 2-nominal pipe, both schedule 40 commercial steel. the 1-nominal pipe contains 3 90° elbows (regular) anda fully open gate valve, all threaded. the pressure drop through the system is 150 kpa. determine the volume flow rate through the system that is horizontally laid.
Answers: 1
You know the right answer?
Develop a preliminary WBS for a small one-story commercial building to be constructed on the site of...

Questions in other subjects:

Konu
Mathematics, 22.03.2021 20:00
Konu
Mathematics, 22.03.2021 20:00