he proposed grading at a project site will consist of 25,100 m3 of cut and 23,300 m3 of fill and will be a balanced earthwork job. The cut area has an average moisture content of 8.3%. The fill will be compacted to an average relative compaction of 93% based on a maximum dry unit weight of 18.3 kN/m3 and an optimum moisture content of 12.9% obtained from the modified Proctor test. Compute the volume of water in kiloliters that will be required to bring these soils to the optimum moisture content.

ansver
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, keigleyhannah30
Aplate clutch has a single pair of mating friction surfaces 250-mm od by 175-mm id. the mean value of the coefficient of friction is 0.30, and the actuating force is 4 kn. a) find the maximum pressure and the torque capacity using the uniform-wear model. b) find the maximum pressure and the torque capacity using the uniform-pressure model.
Answers: 3
image
Engineering, 04.07.2019 18:10, lerasteidl
Determine whether or not it is possible to compress air adiabatically from k to 140 kpa and 400 k. what is the entropy change during this process?
Answers: 3
image
Engineering, 04.07.2019 18:20, RiverH246
Air flows over a heated plate àt a velocity of 50m/s. the local skin factor coefficient at a point on a plate is 0.004. estimate the local heat transfer coefficient at this point. the following property data for air are given: density = 0.88kg/m3 , viscosity 2.286 x 10 ^-5 kgm/s , k = 0.035w/mk ,cp = 1.001kj/kgk. use colburn reynolds analogy.
Answers: 1
image
Engineering, 04.07.2019 19:10, lexie223
Acircular aluminum shaft mounted in a journal is shown. the symmetric clearance gap between the shaft and journal is filled with sae 10w-30 oil at t 30°c. the shaft is caused to turn by the attached mass and cord. develop and solve a differential equation for the angular speed of the shaft as a function of time.
Answers: 2
You know the right answer?
he proposed grading at a project site will consist of 25,100 m3 of cut and 23,300 m3 of fill and wil...

Questions in other subjects:

Konu
Mathematics, 02.10.2019 16:30
Konu
Mathematics, 02.10.2019 16:30