1. What is the productivity rate using cycle time for the following information:
I
Type of Wo...
Engineering, 18.02.2021 03:50 devontemiles8868
1. What is the productivity rate using cycle time for the following information:
I
Type of Work – Hauling
Average Cycle Time – 35 Minutes
Truck Capacity – 25 Tons
Crew - One Driver
Productivity Factor - 0.85
System Efficiency – 55 Minutes
per
Hour
Answers: 2
Engineering, 03.07.2019 23:20, abbz13
Two technicians are discussing the intake air temperature (iat) sensor. technician a says that the computer uses the iat sensor as a backup to the engine coolant temperature (ect) sensor. technician b says that the powertrain control module (pcm) will subtract the calculated amount of fuel if the air measures hot. who is correct
Answers: 3
Engineering, 06.07.2019 03:30, relic7391
The load on a bolt consists of an axial pull of 10 kn together with a transverse shear force of 5 kn. the bolt material has a yield strength of syt syc 100 mpa. find the diameter of the bolt at factor of safety n-0.5, n 1 and n-2 using maximum shear stress theory