What problem of the low-bid process is the negotiated price process intended to solve? O The negotiated price process places a greater emphasis on lowering cost than the low-bid process.
The negotiated price process focuses on contractor qualifications instead of simply seeking the lowest-bidding contractor.
O The negotiated price process is easier to manage than the low-bid process.
O The negotiated price process is faster than the low-bid process.

ansver
Answers: 1

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 03:10, lauriepdx17
What precautions should you take to prevent injuries when dealing with heavy loads?
Answers: 1
image
Engineering, 04.07.2019 18:10, DestyHilBan1183
Adouble-strand no. 60 roller chain is used to transmit power between a 13-tooth driving sprocket rotating at 300 rev/min and a 52-tooth driven sprocket. a) what is the allowable horsepower of this drive? b) estimate the center-to-center distance if the chain length is 82 pitches. c) estimate the torque and bending force on the driving shaft by the chain if the actual horsepower transmitted is 30 percent less than the corrected (allowable) power.
Answers: 3
image
Engineering, 04.07.2019 18:10, siri5645
At 12 noon, the count in a bacteria culture was 400; at 4: 00 pm the count was 1200 let p(t) denote the bacteria cou population growth law. find: (a) an expression for the bacteria count at any time t (b) the bacteria count at 10 am. (c) the time required for the bacteria count to reach 1800.
Answers: 1
image
Engineering, 04.07.2019 18:10, jojoangelique13
The flow rate of air through a through a pipe is 0.02 m5/s. a pitot static tube is placed in the flow. the radius of the pitot static tube is 1 mm. assuming the flow to be steady and the air to be at 300k, calculate the difference in total and static pressure if the diameter of the pipe is: (a) d 0.1 m d 0.05 m (c) d 0.01 m
Answers: 2
You know the right answer?
What problem of the low-bid process is the negotiated price process intended to solve? O The negoti...

Questions in other subjects:

Konu
Mathematics, 10.06.2021 18:30
Konu
English, 10.06.2021 18:30
Konu
Mathematics, 10.06.2021 18:30