What problem of the low-bid process is the negotiated price process intended to solve? The negotiated price process places a greater emphasis on lowering cost than the low-bid process.
The negotiated price process focuses on contractor qualifications instead of simply seeking the lowest-bidding contractor.
The negotiated price process is easier to manage than the low-bid process.
The negotiated price process is faster than the low-bid process.

ansver
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 14:10, cowgyrlup124
Explain the difference laminar and turbulent flow. explain it with the shear stress and the velocity profiles.
Answers: 1
image
Engineering, 03.07.2019 14:10, volleyballfun24
If the thermal strain developed in polyimide film during deposition is given as 0.0044. assume room temperature is kept at 17.3 c, and thermal coefficient of expansion for the film and the substrate are 54 x 10^-6c^-1 and 3.3 x 10^-6c^-1respectively. calculate the deposition temperature.
Answers: 3
image
Engineering, 03.07.2019 15:10, brooklyn674
Apiston-cylinder with a volume of 0.25 m3 holds 1 kg of air (r 0.287 k/kgk) at a temperature of 100 c. heat transfer to the cylinder causes an isothermal expansion of the piston until the volume triples. how much heat is added to the piston-cylinder?
Answers: 3
image
Engineering, 03.07.2019 15:10, theamandawhite
Ahouse has the following electrical appliance usage (1) single 40w lamp used for 4 hours per day (2) single 60w fan used for 12 hours per day (3) single 200w refrigerator that runs 24 hours per day with compressor run 12 hours and off 12 hours find the solar power inverter size in watt with correction factor of 1.25.
Answers: 1
You know the right answer?
What problem of the low-bid process is the negotiated price process intended to solve? The negotiat...

Questions in other subjects: