Engineering, 08.10.2020 09:01 shygrl05
Limestone (calcium carbonate) particles
arestored in 50-L bags. The void fraction of the particulatematter
is .30(liter of void space per liter of total volume) andthe
specific gravity of solid calcium carbonate is 2.93.
a) estimate the bulk density of the bag contents
(kgCaCO3/liter of total volume)
b) estimate the weight (W) of the filled bags. State whatyou
are neglecting in your estimate.
c) the contents of three bags are fed to a ball mill, a
devicelike a clotes dryer containing steel balls. The
tumblingaction of the balls crushes the limestone particles and
turns theminto a powder. The limestone coming out of the mill is
putback into 50-L bags. Would limestone fill three bags, notfill
three bags completely, or fill more than three bags. Explain.
![ansver](/tpl/images/cats/User.png)
Answers: 3
![](/tpl/images/ask_question.png)
![](/tpl/images/ask_question_mob.png)
Other questions on the subject: Engineering
![image](/tpl/images/cats/User.png)
Engineering, 04.07.2019 18:10, Strick1530
Which of the following components of a pid controlled accumulates the error over time and responds to system error after the error has been accumulated? a)- proportional b)- derivative c)- integral d)- on/off.
Answers: 2
![image](/tpl/images/cats/User.png)
Engineering, 04.07.2019 18:10, nandalabella06
True or false (explain) (110)[111] is a slip system in bcc metals . the {111} family in fcc contains 8 planes. resolved shear stress (rss) in single crystals is just related to the applied stress. critical resolved shear stress (crss) in single crystal metals is direct proportional to the number of defects in the structure
Answers: 2
![image](/tpl/images/cats/User.png)
Engineering, 04.07.2019 18:20, samueltaye
Modern high speed trains do not have perpendicular expansion gaps where rails are joined end-to-end any more they are mostly welded together but what might happen if there was a spell of particularly hot weather that causes inspection of the tracks?
Answers: 1
![image](/tpl/images/cats/User.png)
Engineering, 04.07.2019 19:10, ndaha
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
Limestone (calcium carbonate) particles
arestored in 50-L bags. The void fraction of the particulat...
Questions in other subjects:
![Konu](/tpl/images/cats/biologiya.png)
Biology, 17.04.2021 14:00
![Konu](/tpl/images/cats/en.png)
English, 17.04.2021 14:00
![Konu](/tpl/images/cats/fizika.png)
Physics, 17.04.2021 14:00
![Konu](/tpl/images/cats/mat.png)
Mathematics, 17.04.2021 14:00
![Konu](/tpl/images/cats/himiya.png)
Chemistry, 17.04.2021 14:00
![Konu](/tpl/images/cats/obshestvoznanie.png)
Social Studies, 17.04.2021 14:00
![Konu](/tpl/images/cats/en.png)
English, 17.04.2021 14:00
![Konu](/tpl/images/cats/obshestvoznanie.png)
Social Studies, 17.04.2021 14:00
![Konu](/tpl/images/cats/en.png)
English, 17.04.2021 14:00
![Konu](/tpl/images/cats/mat.png)
Mathematics, 17.04.2021 14:00