subject
Engineering, 19.05.2020 05:57 luvberries2276

1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update schedule indicates that a delay of 9 days has been experienced in the execution of Activity B and that a delay to the start of Activity D has consumed this activity’s “free float”. Clearly provide answers (numeric figures accompanied by clear explanations regarding the basis of the numeric figures) to the following:

a) What is the “now” projected total project duration and what drives this new figure

b) Explain the change (if any) to the total float of Activity L?

c) How much free and total floats can still be enjoyed by Activity D?

d) Given the delays described above, and provided that Activities C and F are shown to have been completed but with a joint consumption of 4 out of the 7 days of total float that were originally available to the C-F-K activity chain: (i) what interference (in days) to the scheduling of Activity K can be solely attributed to the completed execution of Activity B? (3 points) And, (ii) what total float can still be enjoyed by Activity K?

2- Given the delay reported to have taken place to the start of Activity D and the flexibility (if any) being now enjoyed (currently under the updated schedule), please argue what circumstances would warrant that the contractor’s PM, in consultation with his site-management subordinates, considers adopting a revised method of work, crew assignment (no. of crews), and/or work-shift schedule, and whether any one or more of these circumstances is/are evident in the updated schedule in connection with the scheduling results newly computed for D.

3- Assume the total duration for the project under study is expressed in months, totaling 14 months, on the basis of adopting a DBB project delivery approach. When will an estimate of this overall duration have been first made? And, what kind of control will be needed regarding this 14-month duration if the owner decides to switch to the “CM at Fee” approach at the point of time when the design phase has reached around 30% completion?

ansver
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, hadellolo8839
Acompressor receives the shaft work to decrease the pressure of the fluid. a)- true b)- false
Answers: 3
image
Engineering, 04.07.2019 18:10, lerasteidl
Determine whether or not it is possible to compress air adiabatically from k to 140 kpa and 400 k. what is the entropy change during this process?
Answers: 3
image
Engineering, 04.07.2019 18:20, samantha636
Avolume of 2.65 m3 of air in a rigid, insulated container fitted with a paddle wheel is initially at 264 k, 5.6 bar. the air receives 432 kj by work from the paddle wheel. assuming the ideal gas model with cv = 0.71 kj/kg • k, determine for the air the amount of entropy produced, in kj/k
Answers: 2
image
Engineering, 04.07.2019 18:20, kendrawalraven
The characteristic roots of a dynamic system are: 1.7920 1.8160 i, -1.7920 1.8160 i, -0.4160 what is the order of this system? what are the settling time and damping ratio of the system?
Answers: 3
You know the right answer?
1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update...

Questions in other subjects:

Konu
History, 02.03.2021 21:50
Konu
Mathematics, 02.03.2021 21:50