The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and absorption of 4.2%, and 899 lb/yd3 of sand having a moisture content of 5.7% and absorption of 1.4%, and 244 lb/yd3 of free water. What is the weight of the mixing water per cubic yard that should be used at the job site? Group of answer choices

ansver
Answers: 1

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, aaliyah80
The drive force for diffusion is 7 fick's first law can be used to solve the non-steady state diffusion. a)-true b)-false
Answers: 1
image
Engineering, 04.07.2019 18:10, mirmir62
Machinery that is a key part of the process and without which the plant or process cannot function is classifed as: (clo4) a)-critical machinery b)-essential machinery c)-general purpose machinery d)-none of the specified options.
Answers: 1
image
Engineering, 04.07.2019 18:20, myahlit84
Inadequate stores control is not an obstacle to effective work order system. (clo4) a)-true b)-false
Answers: 3
image
Engineering, 04.07.2019 18:20, DroctorWellsfan
Inspection for bearing condition will include: (clo4) a)-color b)-smell c)-size d)-none of the above
Answers: 1
You know the right answer?
The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and a...

Questions in other subjects:

Konu
Mathematics, 14.04.2021 06:00
Konu
Mathematics, 14.04.2021 06:00