Consider the following three-station production line with a single product that must visit stations 1, 2, and 3 in sequence:

* Station 1 has five identical machines with average processing time of 15 minutes per job. * Station 2 has 12 identical machines with average processing time of 30 minutes per job. * Station 3 has one machine with average processing time of 3 minutes per job.

a) What are the bottleneck rate rb*,the raw process time To* and the critical WIP wo*? b) Compute the average cycle time when the WIP level is set at 20 jobs, under the assumption of: i) The best case

ii) The worst case

iii) The practical worst case

c) Suppose you desire the throughput of a line to be 90 percent of the bottleneck rate. Find the WIP level required to achieve this under the assumptions of:

i) The best case

ii) The worst case

iii) The practical worst case

d) If the cycle time at the critical WIP is 100 minutes, where does performances fall relatives to the cases? Is thered much room for improvement?

ansver
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, mamasbug4285
An air compression refrigeration system is to have an air pressure of 100 psia in the brine tank and an allowable air temperature increase of 60°f for standard vapor compression cycle temperatures of 77 f entering the expansion cylinder and 14 f entering the compression cylinder, calculate the coefficient of performance a. 2.5 b 3.3 c. 4.0 d. 5.0
Answers: 3
image
Engineering, 04.07.2019 18:20, samueltaye
Modern high speed trains do not have perpendicular expansion gaps where rails are joined end-to-end any more they are mostly welded together but what might happen if there was a spell of particularly hot weather that causes inspection of the tracks?
Answers: 1
image
Engineering, 06.07.2019 03:30, sipstick971
An ammonia compressor has a 5% clearance volume and displacement rate of 80 l/s and pumps against a condensing temperature of 40°c. for two different temperatures of -10°c and 10°c, compute the mass flow rate of refrigerant assuming the clearance volumetric efficiency applies. discharge specific volume corresponding to-10°c and 10°c are 112.5 l/kg and 95 l/kg, respectively.
Answers: 2
image
Engineering, 06.07.2019 03:30, aminsaad4253
Abrayton cycle operates with a regenerator on the air-standard with properties evaluated at 400 k. the tem- perature of the air entering the compressor is 350k while the temperature of the air exiting the compressor is 600 k. the temperature of the air entering the turbine is 1600 k. the overall cycle produced 600 kj/kg of net work out. assuming a regenerator effectiveness of 0.8, what is the temperature of the air before heat addition (combustion)? draw this process on a t - s diagram
Answers: 3
You know the right answer?
Consider the following three-station production line with a single product that must visit stations...

Questions in other subjects:

Konu
Mathematics, 09.12.2020 04:20