Q1) An engineer is considering the 4 machines below for laboratory railway track testing. Using present worth analysis, which machine should be selected? MARR is 8% per year.
Estimates Machine A Machine B Machine C Machine D
Initial cost, $ -144,000 -130,000 -155,000 -94,000
AOC, $/year -10,000 -11,100 -15,000 -1,000
Salvage value, $ 2,500 0 5,000 4,400
Life, years 3 6 3 6

ansver
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 03:10, lauriepdx17
What precautions should you take to prevent injuries when dealing with heavy loads?
Answers: 1
image
Engineering, 04.07.2019 18:10, heidiburgos1own6c0
Fluids at rest possess no flow energy. a)- true b)- false
Answers: 3
image
Engineering, 04.07.2019 18:10, ijohnh14
Shafts are machine elements that are used to a) carry axial loads b) direct shear loads c) transmit power d) rotate at constant speed e) none of the above circular and square shafts subjected to the same torque under the same circum behave a) the same way b) almost the same way
Answers: 2
image
Engineering, 04.07.2019 18:10, genyjoannerubiera
Assuming compressible flow of air and that the measurements are done at flagstaff a pitot static tube that gives the difference of total and static pressure measures 0.35 m of mercury. what is the velocity of air? assume the temperature to be 300k. (submit your excel or matlab calculation sheet)
Answers: 1
You know the right answer?
Q1) An engineer is considering the 4 machines below for laboratory railway track testing. Using pres...

Questions in other subjects: