Engineering, 07.03.2020 17:42 jaylenmiller437

The following data for the activities of a project are available: ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 6 B - 4 C - 7 D A, B,C 5 E A, B,C 6 F D 9 G E 4 H F, G 8 I F, G 6 J H 7 Required: i. Draw the network, number the nodes, find the project completion time and calculate total, free and independent floats for the activities ii. When the activity duration of G is doubled, identify the critical path

ansver
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 14:10, bryneosburn
Line joining liquid phase with liquid and solid phase mixture is known as: a) liquidus b) solidus c) tie line d) none of the mentioned
Answers: 2
image
Engineering, 04.07.2019 16:10, TheOriginalMeyah
An electrical motor raises a 50kg load at a construct velencity .calculate the power of the motor, if it takes 40sec to raise the load through a height of 24m(take g =9.8n/g)
Answers: 2
image
Engineering, 04.07.2019 18:10, meganwintergirl
Afour cylinder four-stroke in-line engine has a stroke of 160mm, connecting rod length of 150mm, a reciprocating mass of 3kg and its firing order is 1-3-4-2. the spacing between cylinders is 100mm. i. show that the engine is in balance with regard to the primary inertia forces and primary 3. a and secondary inertia couples. li determine the out of balance secondary inertia force ii. propose ways of balancing this out of balance force and discuss the challenges that will arise
Answers: 3
image
Engineering, 04.07.2019 18:20, alexis9263
Have a greater impact on maintenance productivity than any other support group. (clo5) a)-the top management b)-inventory and purchasing c)-sub-contracting d)-cmms
Answers: 2
You know the right answer?
The following data for the activities of a project are available: ACTIVITY IMMEDIATE PREDECESSOR DUR...

Questions in other subjects:

Konu
Mathematics, 05.03.2021 23:10