A small-scale silver mine in north Idaho is up for sale by bid. A mining engineer estimates that at current production levels, the mine will yield an annual net income of $80,000 for 35 years, after which the silver will be exhausted.
If an investor’s MARR is 15%, what is the maximum amount that the investor can bid on this property?

ansver
Answers: 1

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, aliopqwas
Condition monitoring is a major component of. (clo4) a)- predictive maintenance. b)-preventive maintenance c)-proactive maintenance d)-reactive maintenance.
Answers: 1
image
Engineering, 04.07.2019 18:20, rocio5649
Amixture of slurry and mud is to be pumped through a horizontal pipe of diameter 500 mm. the fluid behaves as a bingham plastic with a yield stress of 30 pa and viscosity 0.04 pa. s. describe the effects of the shear stress through a transverse section of the pipe by plotting the variation in shear stress and velocity profile: (i) just before the slurry starts to move (ii) as the slurry flows when the pressure gradient is double that in part (i)
Answers: 3
image
Engineering, 04.07.2019 19:10, pjgolden04
How to increase the thermal officiency of an ideal simple rankino cycle? among these methods, which one is the best and why?
Answers: 2
image
Engineering, 04.07.2019 19:10, phantomlizz3233
In general, how do thermosetting plastics compare to thermoplastics in mechanical and physical properties?