Rough riders inc. manufactures jeans in the cutting and sewing process. jeans are manufactured in 50-jean batch sizes. the cutting time is 6 minutes per jean. the sewing time is 15 minutes per jean. it takes 5 minutes to move a batch of jeans from cutting to sewing.
a. compute the value-added, non-value-added, and total lead time of this process.
b. compute the value-added ratio. round to one decimal place.
Answers: 3
Engineering, 04.07.2019 18:10, winterblanco
The higher the astm grain-size number, the coarser the grain is. a)-true b)-false
Answers: 3
Engineering, 04.07.2019 18:10, wyattlb97
Water at the rate of 1 kg/s is forced through a tube with a 2.5 cm inner diameter. the inlet water temperature is 15°c, and the outlet water temperature is 50°c. the tube wall temperature is 14°c higher than the local water temperature all along the length of the tube. what is the length of the tube?
Answers: 3
Rough riders inc. manufactures jeans in the cutting and sewing process. jeans are manufactured in 50...
English, 06.05.2020 07:00
Mathematics, 06.05.2020 07:00
Mathematics, 06.05.2020 07:00
Mathematics, 06.05.2020 07:00