Engineering, 28.11.2019 01:31 Geo777

A120 cy per hr maximum output pump is used to place the concrete for a 200 cy slab. the concrete is supplied by 8 cytransit-mix trucks arriving to the site on 12 min intervals. the concrete batch plant is located 5 miles from the site. averagetruck speed is 30 mph. each transit-mix truck takes, on average, 10 min to discharge. the placement crew size is 7 workers. average worker output is 5 cy of concrete per hr. (a) how long will the operation take? (b) how can the operation bereorganized more effectively?

ansver
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, demarcuswiseman
Calculate the bore of a cylinder that has a stroke of 18 inches and an extension time of 6 seconds at a flow rate of 4 gal/min.
Answers: 3
image
Engineering, 04.07.2019 18:10, krystabrewer3
What are the two (02) benefits, which may result from a successful implementation of preventive maintenance (pm) program in an organization? (clo3)a)- lean manufacturing b)-overlapping responsibilities c)-the planner is not qualified d)-accurate contractor information e)-reduction in equipment redundancies f)-accurate stores information
Answers: 3
image
Engineering, 04.07.2019 19:10, LadyHolmes67
Apressure vessel with an r/t 20 cannot be treated as thin walled vessel. a)-trune b)- false
Answers: 3
image
Engineering, 04.07.2019 19:10, juneham
Estimate the change in specific internal energy au and specific enthalpy h from inlet to outlet for ethylene glycol (a liquid) flowing through each of the following devices: (a) a heat exchanger where the glycol temperature increases from 20 °c to 80 °c; (b) a pump operating at about 25 °c and increasing the glycol pressure from 100 kpa to 8 mpa.
Answers: 2
You know the right answer?
A120 cy per hr maximum output pump is used to place the concrete for a 200 cy slab. the concrete is...

Questions in other subjects:

Konu
Mathematics, 22.03.2021 23:20
Konu
Mathematics, 22.03.2021 23:20
Konu
Mathematics, 22.03.2021 23:20