subject
Engineering, 12.11.2019 07:31 joejoefofana

In a bid package given to a flooring sub, the gc accidently forgot to include a floor plan representing a few rooms totaling 2,500sf. the entire building is 550,000sf. the flooring subcontractor bid the project using the floorplans provided (missing 2,500sf) and signed a contract with the information received. if the scope of the contract states, "provide all flooring in new facility," is this contract enforceable by law? why or why not? 1.

ansver
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 19:30, 10040813
When using the ohmmeter function of a digital multimeter, the leads are placed in what position relative to the component being tested? a. parallel b. control c. series d. line
Answers: 3
image
Engineering, 04.07.2019 03:10, lauriepdx17
What precautions should you take to prevent injuries when dealing with heavy loads?
Answers: 1
image
Engineering, 04.07.2019 12:10, Ryantimes2
On a average work day more than work place firs are reorted
Answers: 1
image
Engineering, 04.07.2019 16:10, TheOriginalMeyah
An electrical motor raises a 50kg load at a construct velencity .calculate the power of the motor, if it takes 40sec to raise the load through a height of 24m(take g =9.8n/g)
Answers: 2
You know the right answer?
In a bid package given to a flooring sub, the gc accidently forgot to include a floor plan represent...

Questions in other subjects:

Konu
Mathematics, 18.10.2019 23:10